One of the eleven Greene King sites, a new 50kW rapid charger alongside the retained AC unit.
The Hart in Northampton was one of eleven sites upgraded under the Greene King programme for RAW Charging: a new 50kW HYC50 rapid DC charger installed alongside the existing 22kW CP4000 AC unit, retained on site.
Delivered on the existing DNO connection with no new grid capacity required, the works covered civils, LV cabling, earthing and bonding, testing and certification through to energisation.
1× HYC50 50kW rapid DC charger installed, 1× 22kW CP4000 AC unit retained.
Delivered on the existing LV supply, no new DNO connection required.
Part of the eleven-site Greene King upgrade programme.
Delivered for RAW Charging.