Gigawatt IndustriesGigawatt Industries
  • About
    • Who We Are
    • How We Got Here
    • Careers
  • What We Do
    • DC Fast Charging
    • AC Charging
    • Grid Connections
    • Civil Engineering
    • Fleet
    • Design
    • Renewables
  • Projects
    • All projects
    • Ongoing projects
  • Insights
  • Clients
  • Get in touch
  • About
    • Who We Are
    • How We Got Here
    • Careers
  • What We Do
    • DC Fast Charging
    • AC Charging
    • Grid Connections
    • Civil Engineering
    • Fleet
    • Design
    • Renewables
  • Projects
    • All projects
    • Ongoing projects
  • Insights
  • Clients
  • Get in touch
Gigawatt IndustriesGigawatt Industries

Full-scope EV charging infrastructure for public authorities, workplaces, fleets and commercial operators across the UK.

Popular links

  • What We Do
  • Projects
  • Insights
  • Who We Are
  • Careers

Contact

  • Unit 7 Blyth Rd, Harworth, Doncaster DN11 8RW
  • 0114 706 9953
  • contact@gigawatt.co.uk
Get in touch

Client Portal

Track your project's progress and access documents any time.

Client Portal

© 2026 Gigawatt Industries Ltd. All rights reserved.

  • Privacy policy
  • Terms of service
  • Accreditations
All projects

Case study

The Willows Shopping Centre.

A full turnkey installation delivered within a live retail car park.

Client
PoGo
Location
Retail
Scope
Turnkey + ICP

What’s on site

Project overview.

A live-site turnkey installation.

Gigawatt Industries delivered a full turnkey EV charging installation at Willows Centre for PoGo, taking the project from early civils through to a fully installed, energisation-ready site.

Working within a live retail car park, our team completed the groundworks required for both the point-of-connection route and the charger infrastructure.

Electrical install and ICP coordination.

We then delivered the electrical installation and integration for 4× 150kW i-charging chargepoints.

Alongside the physical build, we managed the ICP and stakeholder coordination needed for a smooth path to energisation readiness, ensuring quality, compliance and a clear documentation trail for handover.

Key facts

  • Turnkey delivery with ICP coordination, an end-to-end path aligning civils, electrical and connection with no handover delays.

  • Live-site construction approach, works planned around site constraints, maintaining safe public access and keeping the car park operational.

  • Clear sequencing between civils and electrical works, a logical build order reducing rework and keeping the programme predictable.

Gallery

Services used on this project

  • Grid Connections
  • Civil Engineering
  • Design & Engineering

Related projects

All projects
The Centre Livingston case study
Scotland

The Centre Livingston

Gloucester Services Northbound case study
Gloucester, M5 Northbound

Gloucester Services Northbound

Gloucester Services Southbound case study
Gloucester, M5 Southbound

Gloucester Services Southbound

Cardigan Fields Leeds case study
Leeds

Cardigan Fields Leeds

Black Bull Pub, Greene King case study
Newcastle upon Tyne

Black Bull Pub, Greene King

Hinchingbrooke Business Park case study
Huntingdon

Hinchingbrooke Business Park

Let's discuss your project

Talk to us about site surveys, grid capacity, and delivery timelines.

Get in touch today