Case study
Rolling out workplace charging across Tesco distribution centres.
Gigawatt Industries delivered workplace EV charging across Tesco's distribution centres and stores for Pod Point. At the distribution centres, including Doncaster, Daventry and Dagenham, the programme swapped out legacy EV chargers and installed banks of Solo 22kW units on new and existing feeder/switch matrices, with isolators added for safe maintenance.
At the Woolwich store, five Twin 7kW units were installed on an 80A array. Each site was delivered to Pod Point's specification with full testing, commissioning and handover.
Swap-out and installation of Solo 22kW charging units across Tesco distribution centres.
Sites including Doncaster, Daventry (Grocery & Clothing) and Dagenham DCs.
Woolwich store: 5× Twin 7kW units on an 80A managed array.
Isolators and feeder/switch matrix upgrades for safe operation and maintenance.
Delivered for Pod Point.
Services used on this project
Talk to us about site surveys, grid capacity, and delivery timelines.