Case study
Workplace charging for Manchester City at the City Football Academy.
Gigawatt Industries delivered workplace EV charging for Manchester City Football Club at the City Football Academy, working with Pod Point. The installation added four twin EV charging points, two Twin 11kW and two Twin 22kW units, reusing the existing electrical distribution and bases where possible to keep disruption to a minimum.
From cabling and terminations through to testing, commissioning and handover, the works were completed to Pod Point's specification and BS7671, giving staff and players reliable charging at one of the Premier League's most recognisable sites.
Four twin EV charging points, 2× Twin 11kW and 2× Twin 22kW EVCPs.
Delivered with Pod Point at the City Football Academy, Manchester.
Existing bases and distribution reused to minimise disruption.
Full test, commissioning and handover to BS7671.
Services used on this project
Talk to us about site surveys, grid capacity, and delivery timelines.