Case study
A phased workplace charging array at 1000 Aztec West.
Gigawatt Industries delivered workplace EV charging at 1000 Aztec West in Almondsbury, Bristol, for Pod Point (on behalf of EDF).
Across two phases the team installed thirteen Twin 7kW chargers on a three-phase managed array, eight in the first phase and five in the second, with the cabling, protection and commissioning needed to give tenants scalable, load-managed charging across the business park.
13× Twin 7kW chargers installed across two phases (8 + 5).
Three-phase managed array for balanced, scalable charging.
Delivered at 1000 Aztec West business park, Bristol.
Full cabling, protection, testing and commissioning.
Delivered for Pod Point (EDF).
Services used on this project
Talk to us about site surveys, grid capacity, and delivery timelines.