A six-unit workplace array at Uxbridge Business Park.
Gigawatt Industries delivered workplace EV charging at Building 3, Arc Uxbridge Business Park, for Pod Point. The installation added six Twin 7kW chargers on a 100A managed array, fed from a new GRP feeder pillar with switch-fuse, Array load management, surge protection and open-PEN fault detection.
Cabling was routed from the LV panel through new ducting to the array distribution board and out to each charger, before full testing, commissioning and handover, giving tenants scalable, load-managed charging across the car park.
6× Twin 7kW chargers on a 100A managed array.
New GRP feeder pillar with switch-fuse, Array load management and surge protection.
Open-PEN fault detection and dedicated LV feed from the site panel.
Ducted cable routes to an array distribution board serving all bays.
Delivered for Pod Point.